The Data Center Buildout: When Technical Problems Become Business Disputes

November 23, 2026 | Firm News

By Mitchell D. West

Imagine a manufacturer supplies $4 million of cooling or electrical equipment for a $500 million data center. The equipment is installed, but the facility fails an integrated commissioning test. The owner attributes a 90-day opening delay to the manufacturer’s system and demands damages well beyond the contract price.

Was the equipment defective? Was it tested against the agreed specifications? Did another contractor’s work prevent the system from operating? Had the facility’s power or cooling requirements changed after the equipment was ordered? And even if a breach occurred, does the contract make this supplier responsible for the owner’s alleged lost revenue or project-wide delay?

These questions illustrate a central risk in the expanding data-center industry: the value of a supplier’s contribution may be small relative to the losses alleged when a facility cannot begin operating.

Artificial intelligence is accelerating that exposure. The International Energy Agency reported that global data-center electricity demand increased 17 percent in 2025. Developers face a difficult combination of power constraints, long-lead electrical equipment, evolving high-density computing requirements, and systems that must work together before the facility can operate.[1] That combination is creating substantial opportunities for manufacturers, contractors, software vendors, integrators, and commissioning firms—and fertile ground for commercial disputes.

A data center is a system of systems

A modern data center requires reliable interaction among utility connections, transformers, switchgear, uninterruptible power supplies (UPS), backup generators, cooling infrastructure, building-management systems (BMS), data-center infrastructure management (DCIM) software, fire protection, and network equipment. Success depends not merely on whether each component works in isolation, but on whether the integrated facility satisfies its operational requirements.

That distinction matters when a project encounters a problem. A cooling manufacturer might have supplied equipment that performs exactly as specified under assumed conditions, while the facility’s actual rack density exceeds the design baseline. A switchgear supplier may have delivered conforming equipment, but a separate controls configuration prevents successful commissioning. Conversely, an actual defect in a relatively small component can prevent acceptance of an otherwise completed facility.

In either case, identifying the technical problem is only the first step. The more consequential questions are who assumed responsibility for the relevant interface, whether the applicable performance criteria changed, whether the condition actually delayed the project, and what losses the contract permits the other party to recover.

Five pressure points in the buildout

  1. Power availability and energization. A completed building cannot operate without adequate electrical service. Utility connection schedules, substation upgrades, transformer delivery, and load commitments may become critical-path issues. The contract should allocate responsibility for power availability and distinguish the vendor’s delivery obligations from the owner’s or utility’s energization commitments. Seattle City Light’s adoption of a new large-data-center load policy in July 2026 underscores the importance of understanding how local utility requirements may affect development assumptions.[2]
  2. Long-lead equipment. Transformers, switchgear, generators, and related electrical equipment can have procurement timelines that are difficult to reconcile with aggressive project schedules. A late delivery may generate claims for acceleration, extended construction costs, or delayed operation. Before assigning blame, the parties need to distinguish an actual supplier default from specification changes, approval delays, supply-chain contingencies, and the absence of a workable mitigation plan.[3]
  3. Changing computing and cooling requirements. The growth of high-density AI workloads creates pressure to revise electrical and thermal assumptions while a project is already underway. A shift in rack density, coolant requirements, or cooling architecture may affect the very performance baseline against which a vendor is judged. Change-order procedures should address the effect of revised requirements on cost, schedule, test conditions, and warranty obligations.
  4. Software and controls integration. A data center may include equipment supplied by multiple manufacturers operating through interconnected control systems. When the BMS, DCIM platform, controllers, or third-party devices do not communicate as expected, determining the responsible party can require examination of firmware, software versions, network configurations, interfaces, and implementation history. These disputes can also implicate licensing, source-code access, cybersecurity obligations, and ownership of project-specific software.
  5. Commissioning and acceptance. A failed generator load-bank test, UPS test, integrated systems test, or cooling-capacity demonstration can prevent a project from reaching an important milestone. But the test result alone may not establish a breach. The decisive evidence may be the governing acceptance protocol, agreed operating conditions, test instrumentation, the responsibility matrix, and the contemporaneous record of deviations or unresolved items.

When a $4 million contract becomes a much larger dispute

Return to the hypothetical $4 million supplier contract and the alleged 90-day delay. The owner’s demand might include repair and replacement costs, other contractors’ delay claims, extended general conditions, acceleration expenses, extra power or temporary-equipment costs, liquidated damages, lost customer revenue, or lost computing capacity. Those are possible categories of alleged loss, not necessarily recoverable damages.

Whether such a claim succeeds may depend less on the number appearing in the demand letter than on several questions: Was the equipment actually nonconforming? Did the disputed condition affect the project’s critical path? Were there concurrent delays? Did the claimant take reasonable steps to mitigate its losses? Does the contract waive consequential damages or cap liability? Are liquidated damages the exclusive remedy for delay?

The correct answer often requires both a technical causation analysis and a careful reading of the entire contract. A convincing failure report does not, standing alone, establish that every asserted downstream loss is legally recoverable.

The contract provisions that deserve the most attention

For vendors and integrators, several provisions often determine the economic outcome of a dispute:

  • Specifications and acceptance testing. Identify which performance documents control, who conducts the tests, and whether equipment-level or facility-level performance is promised.
  • Schedule obligations and delay damages. Define delivery milestones, extensions of time, notice requirements, liquidated damages, and the relationship between supplier delay and overall project delay.
  • Consequential-damage waivers. Examine treatment of lost revenue, loss of use, customer penalties, and increased operating costs, including exceptions and interaction with liquidated damages.
  • Limitations of liability. Determine whether the cap is based on the contract price, fees paid, insurance proceeds, or another amount—and which claims are excluded.
  • Changes and integration responsibility. Document revisions to system assumptions and allocate responsibility for third-party interfaces and commissioning support.
  • Indemnification, insurance, and notice. Consider coverage, tender obligations, contractual notice deadlines, and limits imposed by applicable law.

These provisions should be reviewed together. A contract with a seemingly clear liability cap can present a different risk if another provision carves out indemnity, warranty, intellectual property, or specified misconduct claims.

The first 72 hours can shape the eventual dispute

When a significant system failure occurs, the operational priority is usually to restore functionality and keep the project moving. That priority is understandable. But fixing the system without preserving its condition can make it much harder to determine what actually caused the problem.

Before a controller is reset, firmware updated, configuration changed, or component replaced, the response team should consider preserving relevant evidence. Depending on the incident, that may include commissioning scripts and results; BMS, SCADA, and DCIM logs; alarms and telemetry; firmware and configuration versions; design drawings; submittals; RFIs; change orders; photographs; service tickets; communications; and schedule updates reflecting the project’s status immediately before the event.

Preservation should be coordinated with necessary safety and restoration work. The objective is not to stop an urgent repair; it is to document the system so that repair does not unnecessarily erase the evidence needed for later analysis.

Contract notice deadlines, potential insurance notifications, and preservation obligations should also be assessed promptly. Where litigation is reasonably anticipated, counsel can help structure a legal investigation and evaluate privilege issues. Involving counsel does not automatically transform ordinary operational records or routine root-cause reports into privileged communications.

Washington-specific considerations

Washington presents additional issues for companies involved in data-center construction and equipment supply. Depending on the nature of the agreement and work performed, RCW 4.24.115 can affect construction-related indemnity provisions; Chapter 60.04 RCW addresses construction lien rights; Chapter 60.30 RCW governs retainage on covered private construction projects; and Chapter 18.27 RCW addresses contractor registration. These rules do not apply identically to every equipment sale, installation contract, and software-services agreement.[4]

Washington also has data-center sales and use tax preferences with detailed eligibility and compliance requirements. RCW 82.08.986 addresses qualifying facilities in rural counties, while RCW 82.08.9861 provides a separate framework for certain qualifying facilities in higher-population counties. Eligible server equipment and certain power infrastructure are covered, subject to statutory conditions. These incentives can influence project budgets and procurement decisions, but eligibility should not be assumed.[5]

Finally, utility-service requirements, local land-use restrictions, environmental considerations, and changes in power planning can affect both the feasibility and timing of a project. Those risks should be accounted for in contracts before delays arise rather than disputed after the fact.

The real challenge is connecting the technology to the contract

Data-center disputes are likely to involve unusually technical records and unusually large economic claims. Resolving them requires more than identifying a defective component. It requires understanding the design assumptions, the allocation of interface responsibility, the actual critical path, the parties’ contractual obligations, and the losses that can be causally and legally attributed to a particular failure.

Equipment suppliers, technology vendors, integrators, contractors, and commissioning firms can reduce their exposure by defining performance baselines clearly, documenting changes, negotiating proportionate remedies, and preserving evidence early when problems arise.

The question is not simply whether something can go wrong during a data-center buildout. In a project this complex, something eventually will. The question is whether the parties can determine what happened, who is responsible, and what consequences they actually agreed to bear.

Mitchell D. West is an attorney with Lowe Graham Jones PLLC in Seattle. His practice focuses on complex business and technology litigation, including disputes involving technical evidence, commercial contracts, trade secrets, and intellectual property. Companies facing significant contract or technology disputes may contact him here.

Notes and sources

[1] International Energy Agency, Key Questions on Energy and AI: Executive Summary (2026) (reporting 17 percent growth in global data-center electricity demand in 2025).

[2] Seattle City Light, Getting Ahead of Data Center Power Demands (June 12, 2026, updated following adoption of the large-data-center load policy in July 2026).

[3] Reuters, U.S. power companies scramble to secure equipment as surging data center demand strains supplies (July 9, 2026) (discussing extended transformer and switchgear procurement lead times).

[4] RCW 4.24.115; Chapter 60.04 RCW; Chapter 60.30 RCW; Chapter 18.27 RCW.

[5] RCW 82.08.986; RCW 82.08.9861; Washington Department of Revenue, Tax Incentive Programs.